Implementation process

The typical implementation timeline for customers is 12-16 weeks, divided into the phases described below.

    1. Preparation Phase (2 weeks)
      • Kickoff meeting
      • Project planning
      • Data mapping and validation
    2. Data Onboarding - Data Readiness (2 weeks)
      • Data discovery
      • Initial extraction
      • Quality sign-off
    3. Data Onboarding - Load & Setup (4 weeks)
      • Data upload
      • Data automation and setup
      • Integration testing
    4. Team Onboarding (2 weeks per module)
      • User training
      • Solution configuration
      • User acceptance testing
    5. Go-Live (2 - 6 weeks)
      • Solution activation
      • Go-live support
      • Performance monitoring
  • Standard Operation and Support (on-going)
    • One annual business review

Customer Responsibilities

For successful implementation, we'll need your assistance with:

  • Appointing a project owner and IT member fully dedicated to Nextail implementation
  • Providing required data in the specified formats and structure
  • Ensuring team attendance at training sessions
  • Validating data accuracy during integration
  • Testing the solutions before go-live

Nextail Responsibilities

Our team will handle:

  • Project management and timeline coordination
  • Technical setup and integration
  • Data validation and quality assurance
  • User training and documentation
  • Go-live support